top of page

PETROKEMYA – SAUDI KAYAN

Pipeline Project

Date of Commencement:

Oct 2012

Client

Petrokemya -Saudi Kayan

Main Contractor:

Waterwag Consultant – Netherlands

Construction Contractor:

Sinopec

Scope of Workt

Front End Engineering & Detailed

Engineering Design:

Process.

Civil / Structure.

Mechanical / Piping.

Electrical.

Instrumentation & Control.

Project Description

Install 8” Export Pipeline to Transfer the Product From

PK to Saudi Kayan.

Products – HC Liquid.

The total length of the pipe line bet. PETROKEMYA and

Saudi Kayan within RC corridor is approximately 15 km.

Installation of one additional pump at Petrokemya.

Installation of one new compressor at Saudi Kayan.

Tie-ins and interfaces in existing MCCs in Substation.

Evaluation of strength and integrity of the supporting

structural elements for installation of new equipment.

Power, Signal, Air, DCS-PLC I/ OS, Control network and

system topology.

bottom of page